NEW POST CREEK HYDROELECTRICAL DEVELOPMENT PROJECT
Fraserdale, ON

CONTRACT VALUE:
$7,600,000
BUILD TIMEFRAME:
10 Months
CLIENT:
Kiewit/Aecon
CONTRACTOR:
CGV Builders – Design Build
JOINT VENTURE:
Taykwa Tagamou First Nation





- Design & construction of a 12,000 square foot powerhouse building to house two 13.5 megawatt, horizontal water turbines and two synchronous generators as a part of the New Post Creek Hydro electrical Development Project.
- The powerhouse building also includes a 100-tonne overhead crane for maintenance purposes.
- The contract also consists in the design & construction of a spillway bridge, a spillway hoist structure, an intake head gate hoist building and an electrical service building.